Contracts

Liquidated Damages

Also known as: LDs, LD

Pre-agreed daily damages payable by the contractor for failing to complete the project by the contract substantial completion date.

Liquidated damages (LDs) are a daily dollar amount written into the contract that the contractor pays for each calendar day the project finishes past the contract substantial completion date. The intent is to compensate the owner for delayed occupancy without requiring the owner to prove actual damages (lost rent, lost business, etc.) in court. LDs typically run $500 to $5,000 per day on commercial work, with larger projects sometimes $10,000+ per day. Public works projects often have schedule-driven LDs because the consequence of late delivery is real public impact.

For LDs to be enforceable, the daily amount must be a reasonable estimate of the owner's actual damages from delay (not a penalty), the actual damages must be difficult to calculate, and the LD must apply only to delays that are genuinely the contractor's fault. Contractors often negotiate to cap total LDs at 10% to 25% of contract value. Excusable delays (owner-caused, force majeure) toll the LD clock; concurrent delay typically does not get LDs assessed against the contractor.

Frequently asked questions

How much are liquidated damages typically?+

Commercial: $500 to $5,000 per calendar day. Major commercial: $5,000 to $15,000 per day. Critical infrastructure: $25,000+ per day on rare projects. The amount must reasonably approximate the owner's actual delay damages to be enforceable.

Are liquidated damages always enforceable?+

Only if the daily amount is a reasonable pre-estimate of actual damages (not a penalty), actual damages are difficult to calculate, and the contract clearly establishes LDs as the exclusive remedy for delay. Penalty-style LDs that bear no relation to actual harm are sometimes voided by courts.

Can a contractor negotiate liquidated damages?+

Yes. Common negotiations: cap total LDs at 10 to 25% of contract value, mutual liquidated damages (owner pays contractor for early completion), grace period (no LDs for the first 7 to 30 days late), exclusion for excusable delay, and offset against bonus payments for early completion.

Related terms